Vertical Pipetting Station User Guide : Maintaining Vertical Pipetting Station : Resolving hardware-related error messages

Resolving hardware-related error messages
About this topic
This topic describes some hardware-related error messages and their possible causes and solutions. For software error messages, see the VWorks Automation Control User Guide.
Communication- or power-related messages
If the communication or power problem persists after you try the solutions or you cannot locate the error message in the table, contact Automation Solutions Technical Support.
 
A command was issued before the Vertical Pipetting Station was fully initialized.
Initialize or re-initialize the Vertical Pipetting Station.
The Vertical Pipetting Station is turned off or the power or serial communication cable is not connected properly.
3
Click Abort, and shut down the Vertical Pipetting Station.
1
Click Abort.
2
In Vertical Pipetting Station Diagnostics, click the Profiles tab, and verify the COM port setting
3
Close the VWorks software.
4
Power cycle the Vertical Pipetting Station by turning off and then turning on the device.
5
Restart the VWorks software.
The Vertical Pipetting Station lost power or communications during a process, or the system encountered an error.
1
Click Abort, and close the VWorks software.
2
Turn off the Vertical Pipetting Station.
4
Turn on the Vertical Pipetting Station.
5
Restart the VWorks software.
1
Power cycle the Vertical Pipetting Station by turning off and then turning on the device.
2
Initialize the Vertical Pipetting Station.
Could not establish communication with Vertical Pipetting Station on COM n.
The Vertical Pipetting Station is not connected properly to the computer, or the serial communication is faulty.
2
Click Abort, and shut down the Vertical Pipetting Station.
The Vertical Pipetting Station was turned on before turning on the Pump Module.
1
Turn off the Pump Module and the Vertical Pipetting Station.
2
Other hardware-related error messages
Locate the error message in the table and try the solution. If the problem persists after you try the solutions or you cannot locate the error message in the table, contact Automation Solutions Technical Support.
 
1
In Vertical Pipetting Station Diagnostics, click the Profiles tab.
2
Verify the selected Head Type matches the installed pipette head, and then click OK.
3
Click Retry.
4
Click Abort.
Verify that the air pressure is within acceptable range. See Laboratory requirements. Adjust the pressure if necessary, and then click Retry.
Shelf n timed out moving in.
3
In Vertical Pipetting Station Diagnostics, click the IO tab, and verify that the tipbox sensor state changes.
4
Click Retry.
Related topics
 
Using Vertical Pipetting Station Diagnostics