The Subprocess (Bravo) () and Subprocess (Vertical Pipetting Station) (
) tasks indicate the start of a protocol subroutine that employs either the Bravo Platform or the Vertical Pipetting Station. Within the subprocess, you can add tasks that are unique to the device. You can expand or collapse the subprocess to show or hide the subprocess tasks.
IMPORTANT All Bravo or Vertical Pipetting Station liquid-handling tasks must be added within a Bravo or Vertical Pipetting Station Subprocess respectively.
IMPORTANT The latest version of the VWorks software is backward-compatible with protocols created in VWorks4 version 6.2.3 or earlier and will continue to support static labware configuration procedures. However, Agilent Technologies recommends that you use the concepts and procedure in Configuring labware when writing new protocols.After adding the Subprocess task at the desired point in the protocol, you have the option of assigning static labware to locations on a device. You assign static labware in the subprocess to override the static labware configuration in the Startup Protocol. For more information about static labware, see Planning labware use.To assign static labware to locations on the device, set the following parameters in the Task Parameters area:
After adding the Subprocess task at the desired point in the protocol, select the task, and then click Device Selection in the Task Parameters area.
1 Double-click the desired device (deck location or shelf) in the Devices available to perform task area to move it to the Devices involved in task area. If you have multiple devices of the same type, you can move them to the Devices involved in task area.
2 If you have multiple devices in the Devices involved in task area, select a device, and then click Use earlier or Use later to prioritize it.
3 Optional. Select backup devices to use in case all of the devices in the Devices involved in task area encounter an error.
a Select Devices in backup pool.
b Drag one or more devices from the Devices available to perform task area to the Devices in backup pool area.
c If you have multiple devices in the backup pool, select a device in the Devices in backup pool area, and then click Use earlier or Use later to prioritize it.
To specify the sequence in which the sub-processes will be performed on the same configured labware:In the following example, the Bravo Subprocess named Dilute is selected.
2
3 In the Sub Process Order area, double-click the subprocess names to rearrange the order.